Rockwood expects to fully spend our ESSER II ($3,516,573) funds prior to June 30, 2023. This includes approximately $2.3 million spent during the 2021-2022 school year and an estimated $1.3 million allocated for the 2022-2023 school year.

all amounts are in dollars ($)
Item 2021/22 (Actual) 2022/23 (Estimate) Total
PPE and other COVID-10 supplies/equipment: custodial equipment, PPE 229,981 231,754 461,735
Student/staff mental health programs: Alive and Well, Hazel Health 313,748 245,713 559,461
Technology: cybersecurity platforms and hardware, outdoor access points, other hardware 747,701 682,297 1,429,998
Indoor air quality enhancements: HVAC ionization and software 780,196 105,563 885,759
Other items in response to COVID-19: touchless POS systems, contact tracing, water bottle filling stations 179,620 - 179,620
Totals 2,251,246 1,265,327 3,516,573

ESSER III funding, which was signed into federal law in March 2021, was officially appropriated by the Missouri State Legislature in February 2022. The district submitted our initial budget application and compliance plan for the $7.9 million on Aug. 23, 2021, and it was approved by DESE on Nov. 15, 2021.  The District has the ability to submit revisions of the budget to DESE for approval.

By the end of the 2022-2023 school year, we estimate that we will have spent or allocated $3.9 million of our $7.9 million ESSER III fund budget. We expect to spend our entire allocation of ESSER III funds by September 30, 2024. Below is a summary of our current budget as approved by DESE:

all amounts are in dollars ($)
Item 2021/22 (Actual) 2022/23 (Estimate) 2023/24 (Estimate Total
Response to COVID-19: PPE, custodial equipment, contact tracing, etc. 162,109 - - 162,109
Accelerated learning: intervention programs, tutoring, and materials 606,678 784,036 754,200 2,144,914
Technology: network hardware - 260,000 - 260,000
Indoor air quality enhancements: HVAC controls and unit replacements - 1,757,500 2,408,334 4,165,834
Reserved for future use - - 302,591 302,591
Total 768,787 3,116,536 4,025,838 7,911,161
         

"The district will continue to carefully plan for the effective use of these one-time funds," said Rockwood Director of Finance Daniel Steinbruegge. "Both short-term and long-term planning for these funds are important, and we have to be strategic in addressing the needs that have been identified as a result of the COVID-19 pandemic. When we have fully spent our ESSER funds, we want to know they made an impact on our students and building environments."